 MASCOT / PROJECT CAPABILITIES & EXPERIENCE

Every station of the mill, engineered end to end

Our EPCC scope covers the full palm oil and agriculture processing line — from fruit/material reception through to storage — plus the civil, structural and utility works that support it.

PROCESSING LINE SCOPE

The full mill process, in sequence


01

Fruit Reception & Storage

Receiving and storing Fresh Fruit Bunches (FFB) delivered from the plantation.


02

Sterilisation Station

Steam sterilisation of FFB under pressure to soften bunches and loosen fruitlets.


03

Threshing Station

Separating sterilised fruit from empty bunches using rotating cylindrical or shaftless thresher drums.


04

Press Station

Digesting fruit into pulp and pressing to extract crude oil from sterilised fruitlets.


05

Depericarper Station

Breaking and conveying fibre and nut separately after the press station.


06

Kernel Recovery Station

Recovering shell and kernel from the fruitlets for further processing.


07

Clarification Station

Collecting and processing crude oil from the press station across multiple clarifying stages.


08

Engine Room & Boiler House

On-site electricity generation and steam generation for power and processing needs.


09

Water Treatment Plant

Treating raw water from the reservoir into clean, process-safe water.


10

Oil Storage Tanks

Bulk storage of extracted crude palm oil ready for dispatch.

TRACK RECORD

Selected contracts

A sample of projects delivered across Malaysia, Indonesia and Papua New Guinea.

CLIENT
LOCATION
SCOPE
Loders Croklaan Asia
Johor
Supply, construction & installation of storage tanks
IOI Speciality Fats
Sabah
Civil, structural, mechanical, piping & insulation for 1,200T refining / 800T fractionation plant, plus bulk storage tanks
Kirana Palm Oil Refinery (KLK Group)
Sarawak
Structural, mechanical & piping works; 1,500T & 4,500T storage tanks
Felda Vegetable Oil Products
Pahang
Mechanical & structural steel works for fractionation plant; refinery/speciality fats contract
Lahad Datu Edible Oils
Sabah
Supply, construction & installation of 1,500T / 3,000T / 5,000T storage tanks, equipment & piping
IOI Bio-Energy
Sabah
Biomass-based cogeneration power plant
Sepik Palm Oil Limited
Wewak, Papua New Guinea
Building structural works & mechanical works for palm oil mill
Tanjung Manis Bulkers
Sarawak
CPO bulk storage tanks, piping & associated equipment
Johor Plantations Group
Kluang
Replacement of empty bunch (EFB) conveyors at palm oil mill

Planning a new mill, refinery or expansion?

Bring us in at design stage for the most efficient scope.

Co. Reg. 41389-T · CIDB G7 · Est. 1978
Engineering strength. Construction excellence.

HEAD OFFICE

PLO 314/205, Jalan Perak Dua,
Pasir Gudang Industrial Estate,
81700 Pasir Gudang, Johor

+607 251 1887 · sales@mascot.com.my


 © 2026 Mascot Engineering & Construction Sdn Bhd (41389-T)